Watch us grow!
Construction Site September 2007


Construction Site September 2007


Social and Behavioral Sciences building


Social and Behavioral Sciences building sketch


Social and Behavioral Sciences Building


View from the Northwest


View from the Northeast


View from Parking Structure


Social and Behavioral Sciences building


Construction Site October 2007 - View of upper pad


Construction Site October 2007 - Lower pad excavation and rebar placement


Construction Site October 2007 - Placement of column rebar


The first concrete pour - concrete placement for lower pad footings


Construction Site October 2007 - Concrete placement and concrete consolidation for footing


Construction Site October 2007 - Completed footing concrete pourr


Construction Site January 2008 - Upper Pad - Note column wall forms. These columns will be poured with grey concrete


Construction Site January 2008 - Lower Pad - Note wall form at lower end of picture.<br>This form is a perimeter wall and will be poured with colored concrete.


Construction Site January 2008 - Wall form prep work at Upper Pad


Construction Site January 2008 - Close-up of Perimeter Wall/Lantern Stair formwork being constructed


Construction Site February 2008 - Upper Pad - Formwork prep continues


Construction Site February 2008 - Lower Pad - Form work in place and colored concrete pour scheduled for 02/08/08


Construction Site February 2008 - Lower Pad - Close-up of wall forms


Construction Site February 2008 - Lower Pad - Wall forms as seen "Inside" of Lower Pad


Construction Site February 2008 - S&BS - Lower pad colored concrete at lantern stair


S&BS - Upper Pad with Vapor Barrier (in Green)


S&BS - 1<sup>st</sup> Floor Deck Slab being Poured (at Lower Pad Area)


S&BS - 1<sup>st</sup> Floor Deck Slab (at Lower Pad Area)


S&BS - Exterior Concrete (at Lower Pad Area)


S&BS - Close-up of Vapor Barrier and Rebar Installation for Slab-On-Grade (Upper Pad Area)


S&BS - Shear Wall Formwork Installation (Upper Pad Area)


S&BS - Upper Pad with Concrete Slab-on-Grade Completed


S&BS - 1<sup>st</sup> Floor Deck Slab with Formwork Installation at Columns (Lower Pad Area)


S&BS - 1<sup>st</sup> Floor Deck Slab


S&BS - Interior Lobby Columns with Formwork Removedbr />


S&BS - Close-up of Interior Lobby Column Detail


S&BS - Upper Pad with 2<sup>nd</sup> Story (East) Deck Under Construction


S&BS - 2<sup>nd</sup> Floor Deck (West) Shoring Installation Underway


S&BS - 2<sup>nd</sup> Floor Deck (West) Shoring and Plywood Installation Underway


S&BS - Lobby View


S&BS - Upper Pad with 2<sup>nd</sup> Story (East) Deck Under Construction


S&BS - 2<sup>nd</sup> Floor Deck (West) Concrete Completed


S&BS - View of Exterior of Building


S&BS - Close-up of Garden Level Ceiling- Mechanical, Electrical, Plumbing Piping


S&BS - Upper Pad with 3<sup>rd</sup> Story (East) Deck Under Construction


S&BS - 2<sup>nd</sup> Floor Deck (West) Concrete Wall Pours Upcoming


S&BS - Construction Stair Towers Erected on East & West Sides of Building


S&BS - Close-up of East End of Project


S&BS - Dichroic Glass Mock-Up/Glass to the Left was approved
for use on the Lantern Stair

for use on the Lantern Stair

S&BS - Close-Up of Dichroic Glass Mock-Up Sample


S&BS - Upper Pad with 3<sup>rd</sup> Story (East) Deck Concrete Pour Completed


S&BS - 2<sup>nd</sup> Floor Deck (West) Concrete Deck Pour Upcoming


S&BS - View from 3<sup>rd</sup> Floor of Project (Looking West)


S&BS - View from 3<sup>rd</sup> Floor of Project (Looking West toward S&BS Unit 2)


S&BS - Upper Pad with 3<sup>rd</sup> Story (East) Deck Concrete Pour Completed. Wall Pours Upcoming


S&BS - 3<sup>rd</sup> Floor Deck (West) Concrete Deck Pour Upcoming


S&BS - 3<sup>rd</sup> Floor Deck Shoring Spanning the Lobby


S&BS - Man Lift Installation


S&BS - Upper Pad with 3<sup>rd</sup> Story (East) Deck Concrete Pour Completed. Wall Pours Upcoming


S&BS - 3<sup>rd</sup> Floor Deck (West) Concrete Deck Pour Upcoming


S&BS - 1<sup>st</sup> Floor Mechanical Duct Installation


S&BS - 1<sup>st</sup> Floor Piping Installation


S&BS - 4<sup>th</sup> Story (West) Under Construction


S&BS - Close-up of 3<sup>rd</sup> Floor (West) Wall Forms


S&BS - Close-up of 4<sup>th</sup> Floor (West) Rebar Installation


S&BS - Garden Level Utilities Installation


S&BS - As Seen from Pereira Drive


S&BS - Close-up of Stair #3 (West) Wall Forms


S&BS - Close-up of Security Camera Installation @ Lantern Stair


S&BS - 1<sup>st</sup> Floor Utilities Installation


S&BS - (East) Roof Shoring & Plywood Installation


S&BS - 5th Floor Deck (West). Note Column Formwork


S&BS - 5th Floor Deck (East)


S&BS - 5th Floor Deck (East) being Prepared for Upcoming Concrete Pour


S&BS - 3rd Floor Deck HVAC and Fire Sprinkler Piping Installation


S&BS - Interior Partition Framing/Furr-Out


S&BS - (East) Roof Concrete Pour Completed


S&BS - 5th Floor Deck (West). Roof Plywood Installation Continues


S&BS - Interior Partition Installation


S&BS - HVAC ductwork Installation


S&BS - HLantern Stair


S&BS - 2nd Floor Deck and Lobby Below


S&BS - Fifth Floor West looking north


ES&BS - East Stair under construction


S&BS - North Lobby Entry facing Pereira Drive


S&BS - Fifth Floor Tenant Improvement Supplies


S&BS - Lantern Stair structure complete


S&BS - Third Floor partition framing


S&BS - Second Floor partition framing


S&BS - First Floor partition gyp board installed


&BS - Garden Level entry ready for primer


S&BS - Garden Level fMRI Procedure Control Room


S&BS - South Arcade receives Brick Veneer and Prep for Stucco Finish


S&BS - South Entry receives 2 story window wall framing


S&BS - Electrical Cables being run to Pod A Supply


S&BS - Fifth Floor receives stucco (white) finish to match windows


S&BS - Your Building As It Stands Today


S&BS - Your Building One Year Ago Today


Exterior Stairwells nearing completion


Exterior finishes @ all stairwells continue


5th floor MEP and priority wall installations continue


Another view of 5th floor MEP and priority wall installations


Double height lobby progresses


Soffits above the lobby doors are complete


Exterior finishes nearing completion


5th floor interior wall framing underway


4th floor walls painted and ceilings being installed


4th floor ceiling installation continues


3rd floor walls painted and ceilings being installed


3rd floor ceiling installation continues


2nd floor ceiling installation continues


2nd floor lobby soffit installation continues


Work catches up where construction elevator once stood


Toilet room tile continues on all floors


Preparation for the accessible ramp and stair underway


Network cabling has begun in the Garden Level


Interior finishes continue at Garden Level


Interior finishes and casework continue at 1st floor


Ceiling installation completed at 2nd floor Lobby


Construction elevator bays continue to catch up


Paint and finishes continue at 4th floor


Framing and insulation installation continues at 5th floor


Site lighting and primary tree placement underway


Site lighting and primary tree placement underway


Garden Level Canopy installation underway


Irrigation system installation underway


Lobby flooring being prepped for Terrazzo


Lobby flooring being prepped for Terrazzo




